SE – BEAR
The OC provided good full time supervision for works contracts. The general standard of workmanship
was good.
NW – Scotland TranServ
Good full-time OC site supervision was noted on all works contract sites visited by PAG. The general standard of workmanship was good.
SW - Amey
The standard of supervision has improved on last year’s good performance, with continued emphasis on health and safety issues on site. The good standard of workmanship has been maintained.
Value study 2 – works contracts
The objective of this value study was to identify trends in tenders, and to examine tender value and the control of final scheme costs. It included those schemes awarded during the year, but which may not necessarily have been completed by the end of 2007/08.
The study looked at a total of 28 works contracts awarded in 2007/08. The total tender value of these works contracts was £48m. A typical works contract in NW is shown in figure 20.
The principal type of works falls into three categories:
• Pavement structural repairs.
• Structures.
• Minor improvements.
The numbers of works contracts in each of these categories are indicated in
Findings The average number of tenderers per works contract in each Unit in 2007/08 ranged from 3.9 to 4.5, which was broadly similar to previous years Trends in tenders The average percentage difference between the lowest and highest tenderer has generally reduced as a whole across the network from 2001/02 to 2007/08 (see
|
Trends in tenders showed: • As with 2006/07, the pre-tender estimates were again very close to the tender award values. The average difference over the four Units was pre-tender estimates being 2.1% lower than tender award values. |
||||||||||||||||||||
|
|||||||||||||||||||||